Studio 3 Final Exam Latest Edition 2025-2026. Questions & Correct Answers. Graded A, Exams of Building and Prefabrication

Studio 3 Final Exam Latest Edition 2025-2026. Questions & Correct Answers. Graded A

Typology: Exams

2024/2025

Available from 07/17/2025

wilfred-mburu
wilfred-mburu 🇬🇧

3.9

(8)

4K documents

1 / 4

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Studio 3 Final Exam Latest Edition
2025-2026. Questions & Correct
Answers. Graded A
_______ is the setting of whatever material is installed in the frames. Often
the material is glass, but porcelain, exposed aggregate plywood, plastic
laminates, and even stone veneer and precast concrete have been set in
the frames. - ANSGlazing
A 2 X 4 sill plate runs around the floor in the following picture. Determine
the purchase quantity and number of board feet of 2 X 4 needed for the sill.
- ANSLength=136 ' ; Board Feet=91 bf
Aluminum and vinyl siding is a common exterior finish for buildings, which
is bid by ______. - ANSsquare (100 sf)
Calculate the the board feet for 475- 2 X 6@16 '0". - ANS7600 bf
Collar ties are used to prevent the rafters of the roof in the following picture
from spreading. The collar ties are 1 × 6s spaced 4 feet on center and are
located one-third of the distance from the ridge of the roof to the top of the
walls. Determine the purchase quantity of 1 × 6 needed for the collar ties. -
ANS9 pieces 8′ long
pf3
pf4

Partial preview of the text

Download Studio 3 Final Exam Latest Edition 2025-2026. Questions & Correct Answers. Graded A and more Exams Building and Prefabrication in PDF only on Docsity!

Studio 3 Final Exam Latest Edition

2025-2026. Questions & Correct

Answers. Graded A

_______ is the setting of whatever material is installed in the frames. Often the material is glass, but porcelain, exposed aggregate plywood, plastic laminates, and even stone veneer and precast concrete have been set in the frames. - ANSGlazing A 2 X 4 sill plate runs around the floor in the following picture. Determine the purchase quantity and number of board feet of 2 X 4 needed for the sill.

  • ANSLength=136 ' ; Board Feet=91 bf Aluminum and vinyl siding is a common exterior finish for buildings, which is bid by ______. - ANSsquare (100 sf) Calculate the the board feet for 475- 2 X 6@16 '0". - ANS7600 bf Collar ties are used to prevent the rafters of the roof in the following picture from spreading. The collar ties are 1 × 6s spaced 4 feet on center and are located one-third of the distance from the ridge of the roof to the top of the walls. Determine the purchase quantity of 1 × 6 needed for the collar ties. - ANS9 pieces 8′ long

Common types of _______are vinyl, polypropylene-woven pile, neoprene, metal flanges and clips, polyvinyl, and adhesive-backed foam. - ANSstripping Determine the length of rafter required for each of the following conditions if the run is 16'0": - ANSA= 16.88' ; B=16.48' Determine the number of 2 × 4 @ 92 5/8″ studs needed for the garage in the following pictures. The studs are spaced 16 inches on center. Add two studs for each door and corner. Ignore the gable ends and studs over the overhead door. - ANS82 studs Determine the number of 4-foot by 8-foot sheets of plywood needed for the floor in the following picture. Ignore the opening. - ANS35 sheets Determine the purchase quantity of 1 × 10s needed for the ridge of the roof in the following picture. - ANS1@12' and 2@14' Doors are grouped according to the mode of their operation. What is the type of operations for A and C in the following table? - ANSBifold, Double swinging Sills are taken off by the_________; the takeoff should be accompanied by notes and sketches that show exactly what is required. - ANSlinear feet

Tyvek is an example of _______ to prevent the infiltration of air and water while allowing water vapor escape the building. - ANSbuilding wrap Using the following picture, what are A, B , C and D in this floor framing system? - ANSGirder, Bridging, Floor joist, and Sill Waterproofing is designed to resist the passage of water and the hydrostatic pressure that occurs when the surrounding soils become saturated. - ANSTrue When any quantity of lumber is purchased, it is priced and sold by the thousand-feet board measure, abbreviated mbm or more commonly mbf (thousand board feet). One board foot is equal to the volume of a piece of wood one (1) foot thick and one (1) square foot. - ANSFalse When lumber is surfaced by planning, it is referred to as ______________.

  • ANSDressed Which of the following sentences is true: - ANSBuild up membrane consists of layers of tar or asphalt and membranes (plies) into a strong impermeable blanket. The waterproofing is provided by tar or asphalt applied between the plies of reinforcement. Wood shingles are usually sold by the bundle with number of bundles required to cover 100 sf ( 1 sq) dependent on the exposure. - ANSTrue