






Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
NICET LEVEL 1 HIGHWAY CONSTRUCTION MIDTERM EXAM LATEST 2025 EXAM ALL QUESTIONS AND CORRECT ANSWERS Acceptance - CORRECT ANSWER >>>The written acceptance by the Department of the Work. acceptance testing - CORRECT ANSWER >>>Testing conducted by the Department to measure the degree of compliance to the Contract actual cost - CORRECT ANSWER >>>The computed cost using calculations provided
Typology: Exams
1 / 12
This page cannot be seen from the preview
Don't miss anything!
Work.
measure the degree of compliance to the Contract
issued after advertisement and before the opening of bids.
payment
Department for the Contract
or any acceptable combination thereof that submits a bid to the Department.
erected over a depression or an obstruction, such as water, highway, or railway, and having a track or passageway for carrying traffic or other moving loads and having a length 3 measured along the center of the structure of more than 20 feet between undercopings of abutments or extreme ends of openings for multiple boxes. Structure dimensions are defined as follows:
stationing from back to back of backwalls of abutments, if present, otherwise end to end of the bridge floor; but, in no case less than the total clear opening of the structure
longitudinal centerline of the bridge between the bottom of curbs, or in the case of multiple height of curbs, between the bottoms of the lower risers or, if curbs are not used, between inner faces of parapet or railing
Contractor after execution of the Contract authorizing one or more of the following: 1. Changes in the Work. 2. Modifications in the basis of payment. 3. Modifications to Contract Time.
subcontractor is responsible for the execution of a distinct element of the work of a contract and carrying out its responsibilities by actually performing, managing, and supervising the work involved, and with respect to materials and supplies used on the contract, prepares the estimate, negotiates price, determines quality and quantity, orders the material, arranges delivery, installs (where applicable), and pays for the material and supplies itself for the project.
Work has been satisfactorily completed in all respects according to the Contract. 2. The Project is ready for use by the Department as required by the Contract. 3. The Contractor has
New Jersey, as created by law, acting through duly authorized representatives, such representatives acting within the scope of the particular duties delegated to them.
Department at 930 Lower Ferry Road, P.O. Box 607 Trenton, New Jersey 08625, or such other laboratory as the Department may designate
unintentional, through which a person in the United States, solely because of race, creed, color, national origin, age, ancestry, nationality, sex (including pregnancy and sexual 4 harassment), marital status, domestic partnership or civil union status, affectional or sexual orientation, gender identity or expression, atypical hereditary cellular or blood trait, genetic information, liability for military service, or disability has been otherwise subjected to unequal treatment.
Department.
not the result of as-built measurement or calculation.
between NJDOT and any applicant and a person for construction work which is paid for in whole or in part with funds obtained from the Federal government or borrowed on the credit of the Federal government pursuant to any program involving a grant, contract, loan, insurance or guarantee under which the NJDOT itself participates in the construction work.
Special Provision document, used for Federal Aid Projects.
the Contractor
use of the final paved portion of roadway throughout the project including but not limited to striping, RPMs, rumble strips, highway lighting, and traffic signals as determined by the RE.
purposes of vehicular travel, including the entire area within the ROW (see Figure 101-1).
inspect the Work for conformance to the Contract
requiring completion by a specified date or within a specified time.
unit or lump sum price.
including but not limited to materials, equipment, personnel, and schedules.
Change of Plan. This includes the version of the Standard Details specified on the key sheet.
the State of New Jersey.
improvement constructed under the Contract.
follows: 1. The areas of construction operations and areas used by the Contractor to perform the work. If only a portion of a lane or shoulder of a road is being constructed, they include all lanes and shoulders of the roadway. 2. Where only one direction of a road is being constructed, and the road is divided by a median, island, or barrier curb, they include all of the lanes in that direction and the median. Otherwise, they include all lanes in both directions. 3. The longitudinals include all safety devices and signs excluding signs greater than 1,600 feet outside the ones shown on the key sheet. 4. Areas within the ROW provided for the Contractor's use.
quantities and kinds of Work to be performed for which bid prices are invited. It also includes the location and description of the Project and the date and time of the opening of bids.
maintained by the Department for use in the Work. Available at the following website: http://www.state.nj.us/transportation/eng/materials/qualified
direct supervision of the administration of the Contract
acquired for or devoted to transportation purposes or construction of a public improvement (see Figure 101-1).
Property Parcel Maps and Entire Tract Maps approved for use in setting the existing and proposed ROW, including setting out or laying out the various easements within which Items are to be constructed or used to enable construction.
specifications, and requirements for the performance of prescribed work which, in addition to the Standard Specifications, is part of the Contract documents.
the performance of prescribed work contained in the Standard Specifications, Special Provisions, and Electrical Materials Specifications as modified by addenda
adjusted through the issuance of Change Orders and the calculation of as-built quantities.
sum bids and products of all quantities for Items shown in the Proposal multiplied by the unit prices bid.
vehicles exclusive of shoulders and auxiliary lanes (see Figure 101-1).
including, but not limited to: electric, water, gas, sewer, fiber optic, communications, and railroad, and the Department with regard to ITS and electrical facilities.
supplies, and incidentals necessary or convenient for Completion by the Contractor of the construction described in the Contract and the carrying out of all duties and obligations imposed by the Contract wholly, or any portion thereof, on the Contractor.
holidays. 2. Days on which the Contractor is specifically required by the Contract to suspend construction operations. 3. Days on which the Contractor is prevented by any conditions beyond the control of the Contractor and adverse to the current controlling operation or operations, as determined by the RE, from proceeding with at least 75 percent of the normal labor and equipment force engaged on such operation or operations for at least 60 percent of the total daily time being currently spent on the controlling operation or operations for all shifts.
calculations, diagrams, illustrations, schedules, performance charts, brochures, and other supplementary plans or similar data prepared by the Contractor or subcontractors, manufacturers, suppliers, or distributors.